11/29/2024, 11:49Karakolsky district power grid department completed scheduled repair work, and the company is ready for the autumn—winter period.
Thus, current repairs were carried out on 34.9 kilometres of electric wires and 207 transformers, as well as major repairs of 42 transformers and 44.1 kilometres of overhead lines. In order to improve the quality of power supply, 13.6 kilometers of old aluminum wires were replaced with modern CIP wires, and 244 old emergency wooden supports were replaced with reinforced concrete ones.
To ensure quality electricity supply in Karakol, 3 new transformers were installed and 3.26 kilometers of 10 kV overhead lines were constructed.
To reduce emergency shutdowns, trees were trimmed along the route of 60 kilometers of overhead lines.
Together with Karakol City Hall, 55 reinforced concrete poles were installed in three new micro-districts and a 250 kVA power center was installed.